Back     Parameters for Product description   Three-phase distribution transformers with rated voltage up to 11 kV    

#Parameter CostLab
1Applied voltage test 100,000/=Electrical Lab
2Check of core and frame insulaion 80,000/=Electrical Lab
3External clearing in air 33,000/=Electrical Lab
4Induced voltage test 80,000/=Electrical Lab
5Insulation of auxiliary wiring 80,000/=Electrical Lab
6Insulation resistance 160,000/=Electrical Lab
7Measurement of no-load loss and current 70,000/=Electrical Lab
8Measurement of short-circuit impedance and load loss 53,000/=Electrical Lab
9Measurement of voltage ratio and check of displacement 162,000/=Electrical Lab
10Technical observations and inspections 100,000/=Electrical Lab
11Winding resistance 82,000/=Electrical Lab
Sub Total: 1,000,000/=
Laboratory Fee: 10,000/=
Total:UGX 1,010,000/=